Client: Gadish/Signature Investment Group

Project description:

The project involved constructing a pedestrian overpass across Ba’al Shem Tov Street in Jaffa. The entire overpass was cast onsite, without prestressed beams. The work included the construction of a transformer room and stairways. The total area paved was about 325 sq m.

Cost: NIS 2.38 million

Date of completion: July 1998