Client: Netanya Development and Tourism Company Ltd.

Project description:

The project involved building a pedestrian overpass across the road leading to Netanya near the Poleg and Shazar intersections. The overpass, 60 m long and 3 m wide, and is suspended from two steel arcs set into concrete foundations on either side of the overpass and on the access structures next to it. It was necessary to construct development walls next to the overpass to support the stairs and access ramp.

Cost: NIS 3.46 million

Date of completion: December 2001